0965 More info . . . 0965 18 May 1914 New Lock and Canal: Third Lock; looking east from guard gate No. 1, backfill being dumped from north wall
0966 More info . . . 0966 18 May 1914 Fourth Lock Excavation: Looking east from cofferdam, backfill of north wall Third Lock in progress
0967 More info . . . 0967 1 June 1914 Fourth Lock Excavation: Looking west from east cofferdam
0968 More info . . . 0968 22 June 1914 New Lock and Canal: Pump house; concrete forms for east face of first story
0969 More info . . . 0969 18 July 1914 New Lock and Canal: Pump house; west basement wall, forms stripped, reinforcement for main floor in place
0970 More info . . . 0970 26 July 1914 Fourth Lock Excavation: looking west from east cofferdam
0971 More info . . . 0971 7 September 1914 New Lock and Canal: Pump house; view looking southeast, showing west and north walls and roof steel erection
0972 More info . . . 0972 2 October 1914 New Lock and Canal: Third Lock; forebay filling valve, first operation
0973 More info . . . 0973 2 October 1914 New Lock and Canal: Third Lock; north side of forebay
0974 More info . . . 0974 2 October 1914 New Lock and Canal: Third Lock; general view looking east from gate No. 3, first filling of lock
0975 More info . . . 0975 3 October 1914 Water Power: Remedial works, MNP Co., scow load of material
0976 More info . . . 0976 15 October 1914 Fourth Lock Excavation: Looking east from 2650 E
0977 More info . . . 0977 15 October 1914 New Lock and Canal: New canal, looking west from about 2600 E
0978 More info . . . 0978 15 October 1914 New Lock and Canal: Third Lock; looking east, first filling to upper level
0979 More info . . . 0979 17 October 1914 New Lock and Canal: Third Lock; removing concrete forms after filling